Browse tasks
View Subprojects | To Do | Gantt Chart | Import/Export CSV
Displaying results 1‒2.
| Task Id | Task Summary | Start Date | End Date | Percent Complete | |
|---|---|---|---|---|---|
| 1000070 | Add ALTER TABLE rules | 2006-05-29 12:00 | * 2006-06-01 12:00 | 25% | |
| 1000072 | Make protopg to be a package | 2006-05-26 14:00 | * 2006-05-29 14:00 | 0% | |
| 1 | 2 | 3 | 4 | 5 |